Tail Assembly

22 FEB 01 and 23 FEB 01 - Trip to Zenith Aircraft factory in Mexico Missouri for the "Rudder Building" class.

01 APR 01 and 02 APR 01 - Trip to Zenith Aircraft factory to pick up tail section kit and plans.

05 APR 01 - Shop preparation and parts inventory

06 APR 01 - Shop preparation

07 APR 01 - Shop preparation.  Began work on Stabilizer rear spar.

08 APR 01 - Completed stabilizer rear spar.  Began work on stabilizer front spar.

12 APR 01 - Continue work on front stabilizer spar.  Corrected rear spar.

13 APR 01 - Completed Stabilizer skeleton.

14 APR 01 - Disassembled, deburred, primed and riveted stabilizer skeleton.

15 APR 01 - Began work on stabilizer skin

22 APR 01 - Drilled and clecoed skin to bottom of stabilizer

23 APR 01 - Removed, deburred, primed and riveted skin to bottom of stabilizer

02 May 01 - Ordered replacement tip rib

11 May 01 - Began work on Elevator, received new tip rib and installed

28 Feb 02 - An Update/ Relocation
 
 